Anggaran Biaya Pembangunan Talud/Rehabilitasi Bencana Alam
Masjid An Nur Sidorejo, Ngestiharjo, Kasihan, Bantul, DIY
No. URAIAN- VOL - HARGA SATUAN - HARGA - TOTAL
1. Pengurugan Tanah 556 m3
Harga satuan : Rp. 77.000 Total point 1: Rp. 42.812.000
2. Pemasangan Batu Gunung 277,9 m3
a. Batu gunung 166,8 m3 @ Rp. 75.000 = Rp. 12.506.400
b. Semen Pc @40 kg 333,5 zak @ Rp. 42.000 = Rp. 14.007.168
c. Kapur 34,18 m3 @ Rp. 175.000 = Rp. 5.982.228
d. Pasir 113.9 m3 @ Rp. 65.000 = Rp. 7.406.568
Total point 2 : Rp. 39.902.364
3. Pekerjaan Beton 8.805 m3
a. Besi Beton o 10 mm 98 bt @ Rp. 60.000 = Rp. 5.880.000
b. Besi Beton o 6 mm 118 bt @ Rp. 18.000 = Rp. 2.124.000
c. Semen Pc @ 40 kg 52 zak @ Rp. 42.000 = Rp. 2.184.000
d. Pasir pasang/cor 4.755 m3 @ Rp. 65.000 = Rp. 309.056
e. Koral 7.22 m2 @ Rp. 70.000 = Rp. 505.407
f. Papan cor 100 lb @ Rp. 7.500 = Rp. 750.000
g. Kawat bendrat 5 kg @ Rp. 13.000 = Rp. 65.000
Total point 3 : Rp. 11.817.463
4. Peralatan Penunjang
a. Pralon PVC Lubang air o 2” 18 bt @ Rp. 37.000 = Rp. 666.000
b. Ember plastic 10 bh @ Rp. 5.000 = Rp. 50.000
c. Seng u/ torong 10 lb @ Rp. 30.000 = Rp. 300.000
d. Paku usuk 10 kg @ Rp. 13.000 = Rp. 130.000
e. Ijuk 15 rol @ Rp. 25.000 = Rp. 375.000
f. Usuk 5/7 X 3m 20 bt @ Rp. 25.000 = Rp. 500.000
g. Benang 1 pak @ Rp. 20.000 = Rp. 20.000
h. Selang 10 m @ Rp. 2.000 = Rp. 20.000
i. Reng 1 ikat @ Rp. 75.000 = Rp. 75.000
Total point 4 : Rp. 2.136.000
5. Biaya Tenaga
a. Pasang Bouplank/ pembersihan 36 m @ Rp. 12.000 = Rp. 432.000
b. Gali Tanah/pondasi 54 m3 @ Rp. 13.420 = Rp. 724.000
c. Pasang batu gunung 277,9 m3 @ Rp. 57.653 = Rp. 16.021.630
d. Pekerjaan beton 8.805 m3 @ Rp. 40.380 = Rp.355.546
Total point 5 : Rp. 17.533.856
6. Pekerjaan Saluran/rehab lain : Rp. 10.000.000
7. Kesekretariatan : Rp. 500.000
8. Biaya Tak Terduga : Rp. 5.000.000
TOTAL ANGGARAN (point 1-8) : Rp. 129.701.638
(TERBILANG : Seratus Dua Puluh Sembilan Juta Tujuh Ratus Satu Ribu Enam Ratus Tiga Puluh Delapan Rupiah)